鲸鱼传媒 recently witnessed two major milestones in its sustainable energy solutions with the African Copper Mine Microgrid Project successfully connected to the grid and the Chowa Mine Photovoltaic-Storage Microgrid Power Generation Project breaking ground in Zambia. These milestones reaffirm its commitment to delivering efficient, green energy solutions worldwide.
African Copper Mine Microgrid Successfully Connected to the Grid
At 18:14 on February 27, as Deng Junbo, Director of 鲸鱼传媒 Silicon Energy Microgrid Research Institute, announced the closing of load switch, the African copper mine microgrid project successfully achieved grid-connected power generation after seven months from project signing to completion, marking the completion of 鲸鱼传媒’s first overseas photovoltaic-storage-diesel microgrid system.
The microgrid comprises an 8MWp photovoltaic (PV) system, a 24MWh energy storage system, and a 3MW diesel generator. By integrating advanced large-capacity energy storage grid-forming technology with state-of-the-art energy management solutions, the system ensures a stable and reliable power supply while significantly reducing operational costs compared to traditional off-grid diesel generation.
According to preliminary estimates, the microgrid is expected to generate over 11 million kWh of electricity annually, reducing carbon emissions by approximately 8,200 tons. This project not only supports the green transformation of the local mining industry but also enhances the region’s energy mix, reinforcing 鲸鱼传媒’s commitment to sustainable development.
Zambia Chowa Mine Project Officially Breaks Ground
Building on the success of its first overseas microgrid project, 鲸鱼传媒 launched its second international initiative—the Chowa Mine Photovoltaic-Storage Microgrid Power Generation Project on March 8, 2025, in Chirundu, Zambia.
Following the signing of the Power Purchase Agreement (PPA) with local partners on January 15, 2025, 鲸鱼传媒 swiftly formed a dedicated international team and employed a strategic procurement approach—primarily sourcing from China while supplementing with local emergency procurement and internal allocation from other project.
By February 18, the first batch of PV modules and mounting structures had been successfully shipped with core equipment arriving at the project site in phases. On March 8, a team of 10 specialized professionals arrived at Zambia, officially kicking off construction. The entire process—from agreement signing to groundbreaking—was completed in just 53 days, showcasing 鲸鱼传媒’s outstanding project management capabilities.
These projects exemplify 鲸鱼传媒 Group’s commitment to integrating Globalization, Digitalization, and Decarbonization. With the focus on the development principle of green and sustainable, 鲸鱼传媒 remains dedicated to driving global energy transformation and contributing to a cleaner, more sustainable future for all.